Split-Module Studio
Concept drawing set · Rev P2 · 12 November 2026

Split-Module Studio

A 4.9 × 6.1 m studio delivered as two ISO 20ft high-cube volumetric half-modules that join down the centreline on site. Each half ships as its own container, so a pair takes one 40ft slot or one 40ft trailer.

Client CanopyProperties Inc.Units mmBasis Philippines (NBCP / NSCP / RA 9514) and EU (EN / Eurocodes), 230 VConcept · not for construction
Half-module2,438 × 6,058 × 2,896
Internal room4,626 × 5,708
Net / gross area26.4 / 29.5 m²
Clear ceiling2,400
Floor to floor2,916
Shipping2 × 20' HC = 1 × 40' slot
Reference buildingsPH 180 · EU 100 studios
L-001

Layout editor

Interactive · drag to rearrange

Drag anything to move it. Drag the corner square to resize. Arrow keys nudge (Shift = ×4), R rotates, Delete removes, Ctrl+Z undoes.

V-001

Japandi 3D walkthrough

Interior visual · open full size
V-002

Installation sequence

Animation · open full size
M-001

Installation method

Site sequence · cranes · tools

Step by step, per pair of half-modules

  1. Before delivery. Podium or ground beams cast with base plates and locating cones at every casting position, set level to ±3 mm and surveyed. Core built ahead of the modules with cast-in tie plates at each floor.
  2. Delivery. Module A and Module B arrive together on one 40ft low-bed trailer, open sides braced, as two 20ft high-cube units. Nothing is unpacked from a container: each half is the container.
  3. Rig. Lower a 20ft container spreader frame onto Module A and lock its four twistlocks into the top castings. Fit two tag lines to opposite corners.
  4. Lift and set A. Lift, slew and lower slowly onto the locating cones. Riggers steer with tag lines only; nobody stands under the load. Check level and position, then release the spreader.
  5. Lift and set B. Same again, landing B beside A with its open side facing A and a 25 mm gap. The locating cones fix the gap and the end alignment.
  6. Final alignment. Correct to ±5 mm with pinch bars, a 10 t hydraulic jack and steel shims under the castings. Check with a laser level or total station.
  7. Lock the base. Weld the bottom castings to the base plates (or lock base twistlocks) and grout.
  8. Remove transport bracing from both open sides, working from inside.
  9. Connect the seam. Fit four bridge clamps at the seam corners (two at floor, two at roof level) from the façade MEWP and the corridor side, and tension them. Then bolt the splice plates across the floor and roof edge beams (3 + 3, Hollo-Bolt M16) and torque to the maker's value. See S-102.
  10. Seal and close the seam strip. The modules arrive fully fitted out except a 380 mm floor strip and 300 mm ceiling band along the seam. Fill the gap with stone wool and intumescent mastic; plug in the power and data seam connectors; join the bedroom blower's refrigerant and condensate pair in the ceiling band (flare or brazed joints), then pressure-test with nitrogen, vacuum and charge the multi-split (certified refrigeration technician; F-gas certified in the EU); close the ceiling band with 2 × 15 fire board, shadow trims and flush access panels; close the floor with an infill deck, underlay, two matching oak seam boards and 3 flush oak access hatches over the plates; fit the vertical wall strips and the glass partition meeting profile. See S-104 and S-105.
  11. Connect services through the corridor wall: water, drainage, sprinkler branch and the sub-meter feed (extract goes out through the façade terminal, not the corridor). Pressure-test water and sprinklers.
  12. Next pair alongside. Place the neighbouring pair on its party-wall side and bridge-clamp castings to castings.
  13. Corridor and ties. Set the corridor slab on brackets fixed to the corridor-side castings and fix steel ties from the top castings to the core plates.
  14. Stack the next level. Drop semi-automatic twistlocks or stacking cones and elastomeric pads into the top castings of the level below, then repeat steps 3–13. See S-103.
  15. Weatherproofing. Roof membrane over the top level, temporary joint tapes between modules, window louvres (condenser niche behind louvre B, extract terminal and fresh-air inlet behind louvre A) checked.
  16. Façade rainscreen. From a MEWP or scaffold, fix rails on brackets to the module façades, then hang the anthracite panels floor by floor with fins over the seams, deep window surrounds, shadow bands at floor lines, the parapet and the podium plinth. The castings and module grid disappear behind it; removable hook-on panels stay over every casting zone. See A-302 and V-002 step 11.

Do the modules need wheels?

  • No. Every module is lifted by crane straight into position. Wheels or skates would add weight and cost, and every module would need them.
  • Fine positioning uses locating cones, tag lines, pinch bars and hydraulic jacks.
  • Only where a crane can't reach the final spot (under an overhang, inside an existing frame) would you slide modules in on machinery skates or air castors. Those are hired tools, not part of the module.
  • In the factory and yard, modules move on a container reach stacker, forklift with container spreader, or a gantry crane.

Cranes

  • Load to plan for: one half-module about 6.5–7.5 t fitted, plus a spreader of about 1 t, so about 8.5 t on the hook with margin.
  • Up to about 4–5 storeys: an all-terrain or truck-mounted mobile crane, typically 100–250 t class, sized by the reach to the furthest module (a 100 t crane may lift only about 8–10 t at 25–30 m radius).
  • 10–15 storeys: a flat-top tower crane with about 8–10 t capacity at the working radius, erected beside the core.
  • A lift plan by an appointed crane supervisor sets the exact model, radius, outrigger loads and wind limit (lifting usually stops above about 9–11 m/s for large flat loads).

Tools and fixings

  • 20ft container spreader frame with four twistlocks; shackles and certified slings as backup
  • Tag lines; radios for the crane crew
  • Locating cones (cast in), stacking cones or semi-automatic twistlocks between levels
  • Bridge clamps for casting-to-casting ties (seam and party wall)
  • Splice plates and blind bolts (Lindapter Hollo-Bolt M16 8.8 or equal), calibrated torque wrench, cordless impact driver
  • 10 t hydraulic jacks, steel shim packs, pinch bars
  • Laser level and total station for setting out and checks
  • Mobile elevating work platform (MEWP) or scissor lift; edge protection and harness anchor points on the roof of each module
  • Welding set for base connections; sealant gun for intumescent mastic
M-001 Installation methodSplit-Module StudioCanopyProperties Inc.Rev P3 · Concept2026-11-02
F-001

Financial model: BOM, ROI and market comparison

Interactive · concept estimates
Market and specification
Market preset
Module specification
Studios in the project
Variant premium USD/studio
Module cost levers (BOM)
Ocean freight USD per 20ft slot
Steel per studio t
Certification spread over studios
Design, engineering % direct
Factory overhead % direct
Contingency % direct
Factory margin % direct
Site and building
Land per m² GFA
Building share: core, lifts, foundations, corridors, roof, site per m² GFA
Efficiency studio gross ÷ GFA, %
Local fees, permits, charges % of hard cost
Income
Rent per studio per month
Occupancy %
Operating costs, tax, insurance % of gross rent
Rent growth % / yr
Finance and exit
Interest rate % / yr
Loan to cost %
Exit yield %
Hold after completion years
Discount rate for NPV %
Traditional build comparison
Traditional build cost per m² GFA
Modular programme months
Traditional programme months
Saved scenarios
Name

Your inputs are kept in this browser.

    Results

    Development cost per studio and project

    Modular vs traditional build

    Traditional cost per m² excludes loose furniture and appliances, so the model adds this spec's appliances and furniture (BOM sections F and H) to the traditional side. Both cases use the same land, fees, rent and finance inputs; only build cost and programme differ.

    Sensitivity: levered IRR

    Module cost by BOM section (USD per studio)

    Savings bridge: INT → Lean EU (USD per studio, package)

    Build cost per m² GFA by market: our system vs traditional (USD)

    Ours = module package (preset spec) + variant premium + building share, spread over GFA at the preset efficiency. Traditional = the preset's published or assumed rate plus the same furniture and appliances (BOM sections F and H), so both bars are like for like. Preset defaults only; your overrides apply to the results above.

    Market presets and sources

    Other modular and volumetric players

    Figures are what the cited sources report; "derived" values are simple divisions of a reported project value by its unit count and include everything in that contract. Most players don't publish prices. The failures listed are the main industry risk: volumetric factories lose money when order books are thin, which is why this plan pairs the factory with CanopyProperties Inc.'s own pipeline.

    Method and caveats

      F-001 Financial modelSplit-Module StudioCanopyProperties Inc.Rev P1 · Concept2026-11-03Not investment advice
      X-001

      Schedules

      All disciplines

      Module schedule

      ItemModule A (left)Module B (right)
      External size2,438 × 6,058 × 2,8962,438 × 6,058 × 2,896
      Open sideRight long side (seam)Left long side (seam)
      ContentsGRP bathroom pod 2,275 × 1,883 with washer-dryer, bed + 2 nightstands, sofa bed 750 deep, coffee table, consumer unit, half of glass partitionEntry door 1,000; consumer unit; kitchen run with fridge-freezer, 2-zone hob over combi microwave-oven, sink with bin under, dishwasher; heat-pump condenser in a boxed niche right of the desk; living blower above the TV; round dining for 4 under TV; desk; wardrobe 1,600 with ELV enclosure; half of glass partition; AC × 2
      Wet servicesPod (WC, basin, shower, washer-dryer) → riser R1Sink, dishwasher → riser R2
      WindowW1: 1,863 × 1,500 tilt-turnW1: 1,863 × 1,500 tilt-turn
      Est. shipping weight6.5–7.5 t (TBC)6.5–7.5 t (TBC)

      Façade and window schedule (all export markets)

      ItemSpecificationCertification / market marks
      ColourAnthracite / dark grey (RAL 7016 or NCS S 7502-B class) on cladding, window frames outside, flashings, copings, sills and grillesColour-fast: through-coloured or PVDF; no repainting
      PH base façadeSite-applied ventilated rainscreen on SFS NVELOPE-type rails, 50–75 cavity, no insulation; anthracite PVDF / coil-coated aluminium cassettes (Hunter Douglas Single Skin Cassette) or coil-coated steel (Colorbond / Philsteel / Union Galvasteel); fins over seams, shadow bands at floor lines, deep window surrounds, parapet and podium plinth; removable panels over castings. Castings and module joints are concealed (A-302).Non-combustible A1/A2 panels; PVDF to AAMA 2605 / EN 13523
      Cladding (INT primary)Through-coloured fibre cement 8–12 mm (Equitone Natura class), ventilated rainscreen on aluminium rails with thermal pads, stainless fixings, 40 cavity, 200 stone wool behindEN 12467 Cat A; EN 13501-1 A2-s1,d0; ASTM E84 Class A / ASTM E136 (US); AS 1530.1 (AU)
      Cladding (PH-sourced alternative)PVDF or premium coil-coated steel/aluminium flat cassettes, anthracite, with long colour warranty (not aluminium composite with PE core)A1/A2; PVDF to AAMA 2605 / EN 13523; colour warranty in writing
      Cavity barriers, membraneOpen-state intumescent cavity barriers at floor and party-wall lines; breather membrane of suitable fire classEN 1366-4 / UL 2079; EN 13859-2
      W1 windowuPVC 70–82 mm multi-chamber, tilt-turn, 1,863 × 1,500; anthracite foil outside, white inside; double-glazed low-e + argon, warm-edge spacer, Uw ≤ 1.3 (≤ 1.0 triple option); laminated/toughened where required; RC2/PAS 24 hardware, opening restrictor, trickle vent, insect screenCE EN 14351-1; UKCA + PAS 24 + BFRC; AS 2047 + AS 1288 (+ WERS); NFRC 100/200 + NAFS (US); Japan: JIS A 4706 window from a Japanese maker (fire-prevention zones need approved fire windows)
      US bedroom escapeClear opening ≥ 0.53 m², ≥ 508 wide, ≥ 610 high, sill ≤ 1,118 (IRC R310 / IBC 1031)US projects only
      Window louvre (every window)Anthracite louvre 1,863 × 700 directly under each sill, inside the same deep window surround; rain-baffle blades aligned to the surround, insect mesh, black insulated blank-off behind unused area. Window B: condenser niche behind. Window A: Ø125 extract terminal (low, right) + fresh-air inlet (left) PH, or MVHR concentric terminal INTFree area ≥ condenser maker's minimum; EN 13030 / AMCA 500-L rain performance; A1/A2
      Window installationIn the insulation plane; pre-compressed tape, airtight inner tape, vapour-open outer tape, sill with end capsRAL guideline / BS 8213-4 / AS 2047 s.8

      Electrical circuits (consumer unit, 230 V, RCBO 30 mA each)

      CctServesRatingModule
      C1Lighting (all)B6A + B via seam connector
      C2General sockets, roomB16 / 2.5 mm²A + B via seam connector
      C3Kitchen counter sockets + combi microwave-oven + fridge-freezer spurB20 / 2.5 mm²B, fridge in A via seam
      C4Induction hob, 2-zone domino (3.5 kW)B20 / 2.5 mm²B
      C9DishwasherB16 / 2.5 mm²B
      C10Washer-dryer (heat-pump)B16 / 2.5 mm²A (pod)
      C5Instantaneous water heater, bathroomB40 / 10 mm² (or 3-phase 16 A)A
      C6Multi-split condenser (isolator in the niche; feeds both blowers)B16 / 2.5 mm²B
      C7Bathroom fan, shaver socket, kitchen under-sink heaterB16 / 2.5 mm²A + B
      C8ELV enclosure, smoke/heat detection supplyB6 dedicatedA

      Sanitary and wet points

      FixtureSupplyWasteRiser
      WC, wall-hung with concealed cisternCW 15DN100R1
      Basin, wall-hung 500 × 380CW/HW 15DN40R1
      Shower 1,300 × 900 in GRP pod, fixed glass screen, linear drainCW/HW 15DN50R1
      Kitchen sink + 5 L under-sink heaterCW 15DN40R2
      Dishwasher, slimline 450CW 15DN40 via sink trapR2
      Washer-dryer, 600, heat-pump (in pod)CW 15DN40 trapR1

      Fire and life safety

      ElementSpec (target)
      Party walls, corridor wall, floor/ceilingEI 60 compartment (REI 90–120 load-bearing at 15 storeys, per national rules)
      Entry doorEI 30-Sa C5, self-closing, intumescent + smoke seals
      SprinklersResidential quick-response concealed pendent, 6 heads; per EN 12845 / EN 16925 (or NFPA 13R where adopted)
      DetectionAddressable optical smoke ×2, heat ×1 (EN 54) on building FDAS; interlinked in-unit sounders
      Fire stoppingIntumescent seals at seam joints, cavity barriers at module perimeters each floor, sleeves at all penetrations
      KitchenFire blanket; heat detector (no smoke detector) near hob
      Bedroom glass partition10 mm toughened safety glass (EN 12150), top-hung sliders, manifestation band at eye level; not fire-rated (inside one compartment)
      X-002

      Design basis and open items

      Read with all sheets

      Design rules used

      • Each half is an ISO 20ft high-cube envelope with ISO 1161 corner castings, so it can carry a CSC plate and ship as a container.
      • Wet services, sprinkler pipework and refrigerant never cross the seam; each half connects to the corridor on its own. The only duct crossing is the kitchen extract branch, through a factory seam duct connector at a ceiling access panel.
      • Only power and data cross the seam, through factory-fitted plug-in connectors in the ceiling void.
      • Units are mirrored in pairs so bathrooms share riser R1 and kitchens share riser R2 across each party wall.
      • Corner posts sit inside the façade and corridor wall zones. Doors and windows stay clear of the seam post zone (2,163–2,463).
      • Open long sides carry temporary steel bracing for transport, removed after setting.

      To confirm with your architect and engineers

      • 15-storey stacking: ISO posts suit static stacking, but lateral stability needs a concrete or steel core. Posts need R90–120 fire encasement, which may thicken walls.
      • EU compliance is set per country (fire classes, accessibility, energy). Above about 18–28 m most states need A1/A2 façades and further controls.
      • Floor cassette: the pod sits in a 60 mm recess so its floor is flush with the oak. All pod drainage leaves at one outlet by the corridor wall.
      • Road height: 2,896 module plus trailer deck must stay within 4.0 m in most EU states, which needs a low-bed or gooseneck chassis.
      • Entry door: 1,000 structural opening, about 900 clear, which meets most EU accessible-entrance rules.
      • Bathroom is a GRP pod (4.0 m² inside). It suits general EU dwelling rules but is not wheelchair-accessible. Some countries restrict combustible pods in buildings over 18 m, so confirm the resin fire class with the pod supplier.
      • Heat pump: inverter multi-split (heating and cooling). Condenser factory-fitted in a boxed niche right of the desk, breathing through an anthracite façade louvre; high-wall blowers above the bed headboard and above the TV.
      • Living area has no window of its own and borrows daylight through the glass partition. Some codes treat bedroom and living as separate habitable rooms that each need direct daylight and ventilation; check whether the partition is allowed, and whether it must stay openable or stop short of the ceiling.
      • Electrical supply: with the 2-zone hob, about 40 A single-phase per unit is enough.